Ceramics Studio Renovation (Kiln)

Insite - HOMEPAGE SLIDE Kiln Ribbon Cutting
 
Updates
Background
Schedule
Map
Project Manager/Vendor Information
  • December 4, 2024

    Kiln Installed

  • November 14, 2024

    Wall Plaster Completed

  • November 5, 2024

    Wall Lath

  • October 21, 2024

    Flatwork at New Kiln

  • September 25, 2024

    Final Concrete Pour Flatwork at New Kiln

  • September 23, 2024

    Rebar Placement for Slab on Grade

  • September 19, 2024

    Back Gate Installation

  • September 17, 2024

    Wall Installation

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer